Page image
Page image
Page image
Page image
Page image
Page image
Page image
Page image
Page image
Page image
Page image
Page image
Page image
Page image
Page image
Page image
Page image
Page image
Page image
Page image
Page image
Page image
Page image
Page image
Page image
Page image
Page image
Page image
Page image
Page image
Page image
Page image
Page image
Page image
Page image
Page image

C.— 4

1929. NEW ZEALAND.

DEPARTMENT OF LANDS AND SURVEY. SWAMP DRAINAGE. REPORT FOR THE YEAR ENDED 31st MARCH, 1929, TOGETHER WITH STATEMENT OF ACCOUNTS.

Presented to both. Houses of the General Assembly 'pursuant to Section 13 of the Swamp Drainage Act, 1915

Sir, — Department of Lands and Survey, Wellington, Ist July, 1929. In pursuance of section 13 of the Swam]) Drainage Act, 1915, I have the honour to forward the report of the Chief Drainage Engineer covering operations on lands proclaimed under the Swamp Drainage Act and amendments. Illustrative plans are also attached. I have, &c., J. B. Thompson, The Hon. G. W. Forbes, Minister of Lands. Under-Secretary for Lands.

REPORT BY CHIEF DRAINAGE ENGINEER, Sir, — I have the honour to submit my annual report on the areas proclaimed under the Swamp Drainage Act, 1915, and amendments. Kaitaia Drainage Area (61,430 Acres), Mangonui County. During the year the Swamp Drainage Amendment Act was passed, the principal provisions being as follows : (1) The area was to be reclassified, and the ratepayers given the right of appeal against such classification ; (2) the striking of rates in the drainage district was suspended until after the 31st March, 1929. In accordance with the provisions of this amending Act two classifiers were appointed, and they have practically completed the classification of all lands within the drainage district. The principal works carried out during the year have been the maintenance of drains, installing of flood-gates, and enlargement of the Whangatane spillway and stop-banks. Rainfall, &c. —Rainfall and river-gauge readings have been recorded daily at Kaitaia, and schedule and graph are attached giving particulars of data obtained. On the 14th May, 1928, 3-20 in. of rain was recorded in a period of eight hours in the Kaitaia Township, but the rainfall in the hill country was at least twice this figure. As a result flood-waters reached the highest level yet recorded up-stream from Kaitaia, and all low-lying areas were inundated. A large part of the country that was flooded remained under water for a few hours only, but the Tangonge basin and surrounding area, also some low-lying land about Awanui, was inundated for several days.

I—C. 4.

C.— 4

2

The following table gives details of rainfall for the past eleven years

Awanui River. —No work was done on this channel except the removal of some snags which impeded navigation below Awanui, and the hauling-out of overhanging puriri-trees and young willows near Kaitaia. A large quantity of sand has been deposited in the lower reaches of this stream during the past twelve months, and the navigation of the channel with vessels of any great draught will become increasingly difficult from this cause. Whangatane Spillway.—Dredger No. 27, Marion steam drag-line, was engaged throughout the year in enlarging this channel on the western side to the extended section required to carry eventual discharge, and dredger No. 18, a Monighan oil-driven drag-line, was engaged for six months in similar work on the eastern side. A distance of 2 miles 10 chains was covered by No. 27 dredge, excavating approximately 149,958 cublic yards of spoil, mostly stiff clay. No. 18 dredge widened for a distance of 76-08 chains, excavating 57,260 cubic yards of spoil, of which approximately half was light peaty soil and the balance stiff clay. Much of the work was carried out in country below or about high-tide level, where the spoil was required for construction of stop-banks. Owing to the presence of water the spoil could not be shaped by machines as excavated, and hand shaping had to be carried out after the spoil had dried sufficiently to stand to the required height at a reasonable batter. Internal drains leading to flood-gates under the banks have also been constructed by hand, and a certain amount of handwork is entailed at bridge-sites, especially as these structures could not be completed in advance of dredging owing to delays in arrival of timber-supplies from Australia. Certain alterations were made to No. 27 dredge, giving greater range and adaptability to the different kinds of work required. This entails operating in soft as well as hard country, cuttings up to 20 ft. in depth, and the handling of heavy timber. This machine is now eminently suitable for the job in hand. Two ten-hour shifts were worked with the of electric light supplied by a steam-driven generating plant. Coal has been delivered on the line of work throughout, and as water is gravitated direct into the boiler through pipe-line laid to the Kaitaia Eiver it is hoped that little time will be lost in operation in the ensuing year. Dredger No. 18 was erected and placed in commission this year, and during six months consistent operation has proved a thoroughly efficient machine for the work required. A new one-yard bucket capable of dealing with stiff clay has been fitted, which, with the provision of " pads " for soft country, is the only alteration found necessary to suit local conditions. Drains.—The principal work in connection with drains has been maintenance, which entails heavy expenditure owing to the rapid and almost continuous growth of many varieties of water-weeds in this locality. Certain drains of flat grade have been cleaned, in spring as well as late autumn, proving of undoubted benefit to the low-lying country served by these outlets. During the late autumn 37 miles of drain was cleaned out, and 5 miles 35 chains was cleaned again in October. Deepening and improvement of drains was carried out on 3 miles 68 chains, and 78 chains of new drain constructed, mostlv in connection with additional flood-gate outlets to the Awanui River. Stop-banks.—The maintenance of 10 miles of stop-bank and drain with eighteen flood-gate outlets was carried out, and 60 chains of new bank was erected on the west bank of the Awanui River, thus continuing the stop-bank system to a point higher up-stream. Six flood-gates, ranging from 18 in. to 3 ft. diameter, were placed in position to give additional outlets to the Awanui River. Five gates were installed to discharge through spoil-bank into the Whangatane spillway, and one culvert was lengthened for this purpose. Three gates were refitted with iron flaps. The shaping of stop-banks thrown up by drag-line excavators was carried on by hand as spoil dried out, and 80 chains of bank completed. About 30 chains of bank constructed of light peaty soil was planted in Kikuyu grass in order to bind and strengthen the embankment. Bridges. —Five sill bridges were erected over outlet drains to serve severances, and the Kareponia Road bridge was raised 3 ft., lengthened 54 ft., and approaches reconstructed to conform to enlargement of the Whangatane spillway. A temporary bridge was erected at this point to carry traffic pending completion of the permanent structure. Buildings, dec. —Two small buildings were erected, one for accommodation of dredge crew of No. 18, and one for storing tools and stores for dredger No. 27. All wooden buildings and surplus plant were painted.

Year. Year 0I ' Wettest Month and Rainfall. Driest Month and Rainfall. Inches. Inches. Inches. 1918-19 .. 47-30 Oct., 1918 .. .. 9-06 Aug., 1918 .. 1-39 1919-20 .. 31-71 July, 1919 .. .. 7-37 Dec,., 1919 .. 0-62 1920-21 .. 53-11 May and Aug., 1920 (each) . . 8-02 Mar.. 1921 .. 1-13 1921-22 .. 49-42 Mar., 1922 ' .. .. 5-84 Jan.,' 1922 .. 2-24 1922-23 .. 44-81 Oct., 1922 .. .. 7-46 Jan., 1923 .. 2-02 1923-24 .. 49-23 Oct., 1923 .. .. 7-92 Dec., 1923 .. 1-38 1924-25 .. 48-89 May, 1924 .. .. 10-34 Mar., 1925 .. 0-51 1925-26 .. 57-90 May, 1925 .. .. 10-43 Feb., 1926 .. 0-88 1926-27 .. 64-91 Oct., 1926 .. .. 9-62 Dec., 1926 .. 1-51 1927-28 .. 55-97 July, 1927 .. .. 11-35 Jan., 1928 .. 0-22 1928-29 . . 58-21 June, 1928 .. .. 9-13 Feb., 1929 . . 0-28

a—4

3

Rainfall & River Gauge Record Waikuruki Bridge (Fosters) Kaitaia River April 1st 1928-March 31st 1929

c.—4

4

Summary of Work done. —Hereunder is a summary of the principal work carried out during the year : Drains cleared, 42 miles 35 chains ; drains widened and deepened, 3 miles 68 chains ; new drains constructed, 78 chains. Dredge cuts —90 ft. completed width, 47 chains ; 60 ft. completed width, 29-08 chains ; 40 ft. completed width, 1 mile 14-27 chains. New stop-banks formed, 60 chains ; repairs to stop-banks, 4 miles. 8 miles. Flood-gates built, 11. Pile bridge erected (temporary), 70 ft., 1 ; pile bridge lengthened from 72 ft. to 126 ft., 1 ; Sill bridges erected—lB ft., 2 ; 14 ft., 3. Buildings erected, 2(1 quarters for men, 1 storehouse for tools, &c.). Fascines used, 80 bundles. Spoil excavated by land-excavators, 207,218 cubic yards. Proposals for ensuing Year.—The principal work in hand for the ensuing year is the widening of the Whangatane Spillway, raising and lengthening of existing bridges, and installation of floodgates to carry local run-off under the spoil-banks and prevent back flow of flood-waters on to the country adjoining the spillway. It is anticipated that the western side of the cut will be completed within twelve months, and work on the eastern side carried to such a point that the spillway may be used to a limited extent, and shortly afterwards to its full capacity. Works Expenditure, and General. —The sum of £25,661 Is. lid. was expended during the year, of which day labour absorbed £8,493 2s. 3d. Some fifteen piecework contracts were let, entailing an expenditure of £1,622 19s. Id. Hikukangi Drainage Area (50,000 Acres), Whangarei County. Rainfall. —The year has been notable for the number of heavy rainfalls, but owing to frequent winds the hill country and roads were not so sodden as usual in winter. The total rainfall for the year at the Ruatangata headquarters was 50-65 in., whilst at Puhipuhi —where the heaviest rainfalls occur — the total recorded was 79-83 in. The heaviest daily fall at the Ruatangata headquarters was 2-84 in., on the 7th July, 1928. whilst at Puhipuhi the heaviest was 5-04 in., on 29th April, 1928. The greatest rainfall at Ruatangata for any one storm was that from the 7th to the 9th July, 1928, inclusive, when 3-99 in. was recorded, whilst at Puhipuhi 8-53 in. fell from the 29th April to the Ist May, 1928, inclusive. A graph showing rainfall and run-off data for the year is attached. Floods.—The highest flood of the year occurred at the beginning of the winter, at the end of April, when the ground was still dry after the summer months. On the 2nd May the maximum flood heights were reached —viz., 33-7 ft. at the Jordan Bridge, 32-5 ft. at Lewis's Bridge, 25-1 ft. at Purua Bridge, 18-5 ft. above G-H Diversion, and 3-7 ft. at lower lagoon. Several more heavy floods occurred during the winter. Although the floods were high during the year, the effect of the still uncompleted works down-stream from the swamp show in the rapidity with which the flood-waters got away compared with former years before the commencement of these works. The plan attached shows the maximum flood levels and the low summer level for the past year. Run-off. —The maximum discharge of the Wairua River at the Ruatangata camp (0 m. 55 ch.) during the flood of the 2nd May mentioned above was in the vicinity of 4,000 cusecs, representing a run-off from the catchment area of 19 cusecs per square mile, or § in. run-off for twenty-four hours ; but the inflow from the tributary streams at their maximum stages was very much in excess of this discharge. The low summer discharge at om. 55 ch. was 45 cusecs, or a run-off of 0-2 cusecs a square mile, or 0-008 in. run-off for twenty-four hours over the whole area. The Whakapara Stream contributed nearly half of this low discharge. River-gauges. —Twelve staff gauges have been installed on the river and tributaries, and one Gurley Automatic Stage Recorder has been installed at the gauging-station at om. 55 ch. Two more are being installed, one at the Jordan Bridge and one at Lewis's Bridge on the Wairua River. With the use of these gauges and the current-meter a fair amount of discharge data has been collected, and during the coming winter careful and frequent gaugings will be made on the river and tributaries to determine the relation between inflow to the swamp area and outflow at flood periods Utilization of the Swamp : Production. —The only two areas to date that are practically protected from flooding are the upper end of the Ngararatunua arm of the swamp and the Mangahahuru Valley. These two areas are now safe from flooding except at the junction with the main swamp, and capable of being brought to a state of full production. The remainder of the swamp is still subject to flooding. Construction Work. —Construction work on the Wairua River and subsidiary channels was pushed on as expeditiously as possible during the yeac, though floods seriously hindered some portions of the work. Wairua River Diversions. —The shovel-work at G-H diversion was completed at the end of April, while the top and bottom ends were opened out to full depth and width by drag-line during the summer. The G-H spillway was also completed by drag-line through the summer. In May, drilling and blasting, followed later by shovel-work, was commenced in the long spillway around the D-B diversion, and up to the end of October 14 chains of rock-excavation was completed. The spoil was tracked down the spillway and across a temporary bridge over the lower end of the D-E diversion to a dump around the edge of the No. 2 lagoon. The amount of rock trucked out was 9,250 cubic yards. At the end of October the machine was equipped as a drag-line and completed the stripping of this spillway, excavating 8,800 cubic yards before being moved to the G-H cut at the end of November. Nos. 1, 2, and 11 rock bars were drilled and blasted in the summer months, No. 1 bar and part of No. 2 bar being excavated by drag-line. The excavation of these rock bars is the heaviest work that the Bucyrus plant could possibly be put on when rigged as a drag-line. From No. 1 bar 2,000 cubic yards of rock was excavated, and from No. 2 bar 1,600 cubic yards.

C.—4,

5

Rainfall Record. 1928-9 Wairua Catchment Area Hikurangi Drainage Works.

C.—4

6

No. 6 diversion was practically completed during the period, some 34,110 cubic yards being excavated. There still remains the rock bar at the down-stream end, and some chains of soft mud where the cut is not down to full depth. No. 7 diversion was commenced through the year. Up to the time that No. 13 Bucyrus had to be moved to Hikurangi to carry on with the Mangawhero Stream improvement work, most of the long toe at the top end and 1| chains of the cut were completed, entailing the excavation of some 3,500 cubic yards. Work will be recommenced on this diversion during next summer. In March No. 13 Bucyrus was moved from the site of the No. 6 diversion to the Mangawhero Stream, and was ready to commence excavation in April. No. 3 Priestman dredge, after leaving the Ngararatunua Canal, worked down the river, and several shallows were removed, and widening done as far as the reach of the machine allowed. Some little distance below Lewis's Bridge the river was very constricted, and widening was carried out there, and will be required at intervals all the way down the river. Approximately 31,250 cublic yards were excavated during the year. Mangahahuru and Mangawhero Diversions. —Good progress has been made with the Mangaliahuru diversion, 137 chains having been completed during the period under review. The cut is 45 ft. wide on top, and 30 ft. wide on bottom, with an average depth of 12 ft. 6 in. The adjoining country is now immune from floods. Before the work commenced every fresh in the stream caused flooding over the main road at McLeod's Flat, but now even the largest floods do not cause it to overflow its banks. A number of small severances were created. The largest severance is to have access by a bridge, as it comprises most of the flat area of the owner's farm. Early in the year the crew of the dredge on this work were placed on a contract basis, which resulted in a great improvement in the output. For the year 114,382 cubic yards were excavated from this diversion, at an average cost of 7-2 d. per cubic yard. Towards the end of November No. 26 dipper dredge commenced the excavation of the branch canal. This is a diversion of the Mangawhero Stream, which flows through Hikurangi Township. This Mangawhero diversion was carried up as far as the stream, a distance of 63 chains, and this point was reached at the end of February. From this point a drag-line will continue the work up through the township. This cut is 32 ft. wide on top, 22 ft. wide on bottom, with an average depth of 10 ft. One large severance has been formed, necessitating access being given by a bridge. The total excavation in the Mangawhero diversion was 42,110 cubic yards, at a cost of 9d. per cubic yard. Okarika Diversion. —The progress of this work was greatly hindered by frequent flooding of the low land through which No. 12 Bucyrus drag-line was working, but by the end of the period the machine had crossed the Otakairangi Road and reached om. 76 ch., covering a distance of 67 chains during the period. This cut has an average width of 50 ft. on top, 25 ft. on bottom, and an average depth of 10 ft. The country proved to be very " rotten," there being a clay surface underlain by peat. Two bad slips occurred near 0 m. 58 ch. and 0 m. 72 ch. respectively, due to the inability of the country to hold the spoil and to withstand the vibration of the machine when digging. The' total quantity of spoil excavated by No. 12 drag-line during the period was 70,425 cubic yards, at the rate of 11-Bd. per cubic yard. A contract for the excavation of 3 miles 48 chains of hand drain up the Okarika Valley was let in December, and work was commenced early in January. To date 1 mile 72 chains have been completed. The lower end of this drain is intended to dry out the country ready for machine excavation. The Okarika Valley, which divides into two main arms, is all peat country, and by continual hand draining the peat will be consolidated. There is a considerable area of Crown land in the Okarika Valley, some of which will be suitable for farming, and the remainder for either flax-growing or farming. Otonga Outlet. —The Otonga arm of the swamp has been thoroughly explored during the period, and the main outlet located. The draining of this arm will have to be carried out by hand for some years, as the peat will have to be consolidated before it can hold a machine. The main-drain location runs from the river at the upper end of No. 11 diversion to the main North Road at Otonga. The swamp it drains is mostly peat, in some places of great depth, though in others it is shallow, and adjoining the river the country is solid. The peat is generally very firm, and should make good soil when drained and worked up. Where the swamp narrows as it runs up to Otonga there is a creek which was full of water, arid resembled a lagoon rather than a creek. Recently an underground subsidence took place under this creek, and the water drained the lagoon by running underground, and this contributed in a small measure to the flooding of the Hikurangi Coal Co.'s mine. The mine company sealed the subsidence, and the main drain to be put in by the Department was so located that the water will be diverted away from the site of the subsidence. A contract was let for the construction of 10-5 chains of hand drain, and this has been completed. A further 2 miles 53 chains of drain will be put in hand shortly. Ngararatunua Canal.—The cleaning of this canal was commenced in March, and by the end of the period 160 chains had been completed. Summary. —The following is a schedule of some of the works completed during the past year : Dredge cuts cleaned, 2 miles ; drains constructed, 2 miles 30 chains ; dredge cuts constructed, 3 miles 36 chains ; levels taken, 134 miles 37 chains ; traverses run, 64 miles 27 chains ; peat soundings, 391 ; river cross-sections, 559; pile bridge erected, 120 ft., 1 ; temporary bridge erected, 84 ft., on stone and netting piers, 1 ; buildings, additional room on office and chaff-shed, 2 ; spoil excavated by floating and dry-land excavators, 312,377 cubic yards ; rock excavated, 10,600 cubic yards ; stiff clay and rubble excavated, 231,352 cubic yards ; soft clay and peat excavated, 70,425 cubic yardfs.

7

C.—4

Programme of Work for Coming Period. Wairua River. —Before the flood period arrives No. 14 Bucyrus will return to the long spillway around the D-B diversion to work as a shovel, and it is anticipated the spillway will be completed within six months. When the spillway is completed the large slip at the mouth of D-B diversion will be removed, and the machine will concentrate on the removal of the bars and shallows in the river, working up-stream and lowering the water-level in successive steps. No. 14 will move up-stream gradually in carrying out this work. The removal of bars and shallows and the bringing of the river to an even width from Lewis's Bridge down-stream will be carried out by the Priestman, which is at present engaged on this work. By this means, and by working up-stream, as mentioned above, it is hoped to have a number of the obstructions removed by the end of the next period. After No. 13 Bucyrus has completed the Mangawhero Stream improvements it will return to No. 9 diversion of the river and commence excavation at that point. The site is now being cleared and stocked with coal. When No. 12 Bucyrus has excavated the Okarika diversion as far as possible before the coming of winter, it will be shifted to No. 10 diversion of the river in order to commence excavating there. Okarika Diversion. —No. 12 Bucyrus is to excavate some distance farther, and before the advent of winter will proceed to No. 10 diversion of the river. The hand-drain contract will be completed in April or May. This drain will be deepened and possibly enlarged next summer, as the peat will have subsided considerably by then. Mangahahuru Diversion. —This will be completed during the coming period. There is a considerable amount of scrub at the lower end of the location, and a contract has been let for the clearing of same. Mangawhero Diversion.—This work will be completed up through the township by No. 13 Bucyrus within about four months, and should absolutely eliminate all danger of flooding there. Otonga Outlet. —The main outlet drain will be proceeded with, and contracts will shortly be let for its completion by hand-work. Next summer the portion of the outlet through the peat country can be deepened as required. Waiotu Stream. —Detailed surveys of the Waiotu Stream from Hukerenui down to the junction with the Whakapara Stream will shortly be made, as this will be a suitable work for No. 26 dredge after it has completed the Mangahahuru diversion. Excavating Machinery. No. 12 Bucyrus. —This machine, equipped as a drag-line with a 41 ft. jib and a 1 cub. yd. bucket, has been working on the Okarika diversion except when laid up on account of floods. This machine is in good running-order, though the boiler will require retubing at an early date. No. 13 Bucyrus. —This machine has been engaged on drag-line work all the period, using a 50 ft. boom and a f cub. yd. bucket. The boiler was completely retubed, and the machine is now in good running-order. Most of the year was spent on No. 6 diversion. No. 14 Bucyrus. —Until October this machine was working as a shovel in the long spillway round D-B cut, but since then it has been equipped as a drag-line with 50 ft. jib and a 1 cub. yd. bucket excavating clay and blasted rock from the bars in the river. The machine has been kept in good order. No. 3 Priestman.—Early in the period, whilst proceeding down the river from the Ngararatunua Canal, the pontoon struck and was holed by a hidden snag, and she sank in fairly deep water. In July arrangements were made with the Auckland Harbour Board for the loan of their diver, who was engaged on the salvage operations for some three weeks, and on the 6th August the dredge was refloated. Since then she has been proceeding down-stream, removing bars, shallows, &c. No. 26 Dipper Dredge.—This dredge has been engaged on the Mangahahuru and Mangawhero diversions, and has excavated 156,492 cubic yards for the period. At the middle of March the Diesel engine was removed, and the engine from No. 25 dredge, which has been overhauled, was installed. Some difficulty was experienced in putting the substituted engine in running-order, otherwise the plant has been kept in good order. Drilling and Compressor Plant. —One compressor was transferred to the Rangitaiki works during the period. The remaining six compressors and the drilling plant have been in fairly constant use in the spillway, rock bars, and at the shops. Locomotives and Rolling-stock. —These were in use for the first half of the period until No. 14 was converted to a drag-line for the removal of rock bars, &c. Another locomotive will shortly be transferred from Hauraki Plains, as the haul will be long when shovel-work is recommenced, and a third locomotive will speed up the output. The plant is all in good order. Motor Truck and Cars.—There are at present on the works one Thorneycroft 2-ton lorry, one Ford 30 cwt. lorry, two Ford touring-cars. The Thorneycroft lorry will shortly be transferred to Hauraki Plains. The Overland car was sold to a local settler. Workshops.—These have been kept busy all through the period. A large variety and amount of repair work has been done here, and many machine parts have been made in the shops. On account of the heavy nature of the work on which the machines are engaged the repair work is heavy, and buckets continually require repairs. Drill-steel sharpening is a large item in the work, and a considerable amount of bridge ironwork was made during the latter part of the period. It is anticipated that with the completion of the long spillway next summer the workshops and most of the camp will be shifted up to the swamp near Apotu, where a site has already been selected.

c.—4

8

Other Works. Bridges. —A settler's access bridge over No. 6 diversion of the river, 120 ft. long, was completed recently by contract. A temporary tramway bridge, 84 ft. long, over the mouth of the D-B diversion, was constructed early in the period, to provide access from the spillway to the dump. Materials are on the ground ready for the commencement of construction of two settlers' access bridges —viz., one, 40 ft. long, over the Mangawhero diversion, and one, 48 ft., over the Mangahahuru diversion—and also a road-bridge, 58 ft. long, over the Okarika diversion. Surveys.—The new engineering survey of the Wairua River, which was commenced at the end of the previous period, was completed in October. Complete and accurate engineering data for the river is now available. On the completion of the river survey two parties were in the field, one investigating the Otonga arm of the swamp and the other on the Riponui arm of the swamp. Roth of these areas were thoroughly investigated, and the main outlet channels located. Plan work for all these surveys is almost completed. During the coming year an engineering survey will be made of the Ngararatunua arm of the swamp, the Waiotu Stream and adjoining swamp area, and the Whakapara Stream. Compensation Claims. Quite a number of claims for compensation for loss of land, &c., have been received during the year, and a fair number can be expected to come in during the coming year. Works Expenditure. The expenditure recorded for the year totalled £24,272 19s. 10d., of which £12,654 10s. lOd. was paid in wages. Waihi Drainage Area (20,000 Acres), Tauranga County. It was pointed out in my last report that rates covering both capital and maintenance expenditure had been struck for the 1927-28 rating-year. However, an amendment of the Swamp Drainage Act was passed in 1928 suspending the collection of drainage rates on this area until after the 31st March, 1929. This amendment also provided for a reclassification, giving ratepayers the right of appeal against such classification. The two classifiers were appointed, and they completed their classification of all lands towards the end of the period under review. The work carried our during the year consisted almost entirely of maintenance and improvement of existing works. Towards the end of the period a Monighan drag-line was transferred from the Rangitaiki drainage-works in order to carry out the widening and deepening of the Kaikokopu Stream as scheduled, from the East Coast railway-line to the end of the previous dredging, and also minor dredging at the mouth of the Mangatoetoe Stream. This work will be pushed on as quickly as possible, and when completed will afford much-needed relief to an area previously waterlogged in wet seasons. Whilst the dredge is in the locality the opportunity will be taken to remove the accumulation of pumice in a length of the Wharere Canal. It will probably be found necessary to carry .the dredging of the Kaikokopu to the north of the main road for some distance in order to remove the pumice brought down by the dredging above mentioned. Dredges.—The only dredge employed was Monighan No. 17, and the distance dredged by this plant in the short time worked was 11 chains, a total of 12,100 cubic yards of spoil being removed. The American steel dipper dredge hired to the Kaituna Drainage Board was returned by the Board to The Mount Wharf, Tauranga, where it was dismantled and stored. Maintenance. —This work, which includes the patrolling of stop-banks and flood-gates as well as the genera] maintenance of hand drains, is now supervised by a working foreman. This man also has the care of the departmental property still remaining on the works. During the year 37 miles 14 chains of drains were cleaned, and 2 miles 26 chains of drains deepened. Flax Leases. —Milling has been carried on continuously through the season by the company leasing the bulk of the Crown land on the area. The subsidence of much of this country following drainage is making desirable the construction of an increased number of subsidiary drains to prevent the waterstagnation which is fatal to successful flax-growing. Where the areas are provided with sufficient drainage the flax is making a very healthy growth, but the growth is disappointing in places where it is apparent the land lacks internal drainage. A certain amount of clearing and drainage has been carried out in the small flax leases west of the Wharere Canal, but probably the unstability of the hemp-market is a factor influencing the development of this country for flax-growing purposes. Fires. —The damage from fires is ever present on a flax area, and only the vigilance of lessees has prevented serious consequences following several outbreaks during the year. As pointed out on previous occasions, it would seem that the necessary legislative authority should be granted empowering the constitution of fire districts on flax-bearing lands. Buildings.—These consist of a store-shed and workshop, two cottages, and foreman's quarters. The three first named of these are leased to the flax-milling company operating on the area. Levels. —During the year levels were run over all the drains and canals in the area for record purposes. A total of 68| miles of levels and 30 chains of traverse were run during the year. Future Works. —Kaikokopu, Mangatoetoe, and Wharere dredging, and the maintenance and minor improvement of existing works. Works Expenditure. —The total expenditure for the year was £3,395 9s. Id.

9

C.—4.

2 -C. 4.

Poukawa Drainage Abba (13,567 Acres), Hawke's Bay County. Towards the end of the year it was decided to proceed with the alternative drainage scheme of •developing the area as a flax-growing proposition. Briefly, the scheme is to lower the summer level of Lake .Poukawa by some 6 ft. by constructing a main channel, and leave the subsidiary drainage to the settlers interested. The dredge pontoon constructed in 1916 was naturally in a very bad state of repair, and the first work put in hand was the reconditioning of this pontoon. After this work had been carried out the Priestman dredge machinery and chutes were railed from Auckland and re-erected. At the end of the period under review the dredge commenced operations, and it is anticipated good progress will be made henceforth. Other minor works comprised building coal-punt, 18 ft. by 7 ft. 6 in., and repairs to road and two bridges through private property to ensure safe cartage of heavy machinery. The buildings, comprising cookhouse, office, and tool-shed, have been placed in good order. The expenditure recorded for the year totalled £785 Is. sd. I have, &c., E. G. Macmorran, Chief Drainage Engineer. The Under-Secretary for Lands, Wellington.

C.—4.

10

SWAMP LAND DRAINAGE ACCOUNT. Receipts and Payments Account for the Year ended 31st March, 1929. Receipts. £ s. d. Payments. Balance as at Ist April, 1928 .. .. .. 19,262 18 0 Kaitaia Drainage District— £ s. d. £ s. d~ Debentures issued under Swamp Land Drainage Drainage-works, &c. .. .. 11,456 12 5 Act, 1915, and Appropriation Act, 1918, section Management and engineering 46 .. .. .. .. .. 35,000 0 0 expenses .. .. .. 958 14 5 Temporary transfers from other accounts (Public 12,415 6 10 Revenues Act, 1926, section 40) .. .. 15,000 0 0 Waihi Drainage District — Rents from the letting of national-endowment Drainage-works, &c. .. .. 2,060 4 10 lands in the Waihi drainage area .. .. 2,245 13 8 Management and engineering Special rate for interest and sinking expenses .. .. .. 98 4 6 fund: Swamp Land Drainage 2,158 9 4 Act, 1915, section 5 — £ s. d. Hikurangi Drainage District— Kaitaia drainage area .. 69 13 6 Drainage-works, &c. .. .. 15,695 15 6 Waihi drainage area .. .. 10 11 Management and engineering 70 14 5 expenses .. .. .. 1,424 13 11 General rate for administration and 17,120 9 5 maintenance : Swamp Land Drain- Poukawa Drainage District— age Amendment Act, 1926 (5) — Drainage-works, &c. .. .. 504 0 7 Kaitaia drainage area .. .. 18 611 Management and engineering Waihi drainage area .. .. 017 7 expenses .. .. .. 42 17 9 19 4 6 | 546 18 4 Rents .. .. .. .. .. 119 17 4 I Fuel and stores .. .. .. 11,209 2 8-Plant-hire .. .. .. .. .. 55 0 0 | Interest on debentures recouped to Royalty .. .. .. .. .. 117 8 Consolidated Fund .. .. .. 1,660 0 0 Interest on mortgage .. .. .. 10 10 0 Loose tools .. .. .. .. 12 15 0Repayment in reduction of mortgage .. .. 50 0 0 , Management charges on ConsoliInterest on investments .. .. .. 338 17 11 j dated Stock .. .. .. 7 12 2 Interest on temporary transfers charged during Stamp duty on transfers, Consoliyear 1927-28 .. .. .. .. 1,145 11 9 dated Stock .. .. .. 14 9 4 Miscellaneous .. .. .. .. 918 16 2 22 1 6 Plant and machinery, &c. .. .. 4,807 13 1 ! Refund of special rates for interest and sinking fund— Kaitaia drainage area .. 337 14 0 Waihi drainage area .. .. 4 10 11 342 4 11 Refund of general rates for administration and maintenance— Kaitaia drainage area .. 109 13 1 Waihi drainage area .. .. 161 19 7 271 12 8 Temporary transfers from other accounts repaid.. 15,000 0 ft Balance at the end of the year—Cash in the Public Account .. .. .. .. 8,672 7 8 £74,239 1 5 £74,239 1 5

11

C.—4

SWAMP LAND DRAINAGE ACCOUNT—continued. Balance-sheet as at 31st March, 1929. Liabilities. Assets. Debentures issued under Swamp Land Drainage £ s. d. Kaitaia Drainage District— £ s. d. £ s. d. Act, 1915.. .. .. .. .. 571,000 0 0 Allocated cost of works on which Temporary advances from other accounts (section rates are levied— 40, Public Revenues Act, 1926) .. .. 10,000 0 0 Rural subdivision .. .. 110,000 0 0 Consolidated Fund —For loans redeemed under Town district .. .. 15,000 0 0 Public Debt Repayment Act, 1925 .. .. 5,000 0 0 125,000 0 0 Public Works Fund—Land Improvements vote .. 4,563 J9 7 Excess cost of works not reConsolidated Fund — Interest on debentures paid eoverable .. 62,696 7 3 but not recouped from Swamp Land Drainage Interest Account —Proportion Account .. .. .. .. .. 49,790 2 8 chargeable to district .. 69,417 14 5 Consolidated Fund—Accumulated interest on 132,114 1 8 amount expended out of Public Works Fund .. 2,743 10 2 Waihi Drainage District — Sundry creditors— £ s. d. Allocated cost of works on which Interest on debentures accrued i rates are levied .. .. .. 75,000 0 0 but not due .. .. 8,913 14 0 ] Excess cost of works not reInterest on temporary transfers 1,413 10 7 | eoverable .. .. 5,500 10 4 Departmental .. .. 352 10 6 I Interest Account — Proportion Miscellaneous .. .. 5,770 8 4 ; chargeable to district .. 27,778 19 9 16,450 3 5 I 33,279 10 1 Rent accrued but not due ... .. .. 298 0 0 ! Poukawa> Drainage District— Suspense Account .. .. .. .. 5,557 11 6 | Drainage-works .. .. 5,121 110 ! Interest Account — Proportion chargeable to district .. 2,115 11 11 7,236 13 9 i Hikurangi Drainage District— Drainage-works .. .. 162,784 18 6 Interest Account — Proportion chargeable to district .. 41,833 9 2 204,618 7 8 Mangawai Drainage District— ! Drainage-works .. .. 1,877 15 9 Interest Account — Proportion chargeable to district .. 616 8 4 2,494 4 1 Harihari Drainage District-Drainage-works .. .. 4,354 15 1 Interest Account — Proportion chargeable to district .. 1,141 6 11 5,496 2 0 [ Buildings .. .. .. .. 2,611 4 6 I Wharves .. .. .. .. 85 1 9 Plant and machinery .. .. .. 48,650 6 9 Loose tools .. .. .. . . 762 3 4 Live-stock .. .. .. .. 28 4 5 Fuel, &c. .. .. .. .. 2,854 5 11 Stores on hand .. .. .. 6. S4B 1 5 Sundry debtors — £ s. d. Advance on mortgage .. 160 0 0 Interest on mortgage .. 2 15 Hut rents .. .. .. 16 9 3 Dredge-hire .. .. 940 10 0 Rent under section 4 (5), Swamp Drainage Amendment Act, 1926 .. .. .. 268 17 1 Departmental .. .. 700 15 3 Miscellaneous .. .. 51 17 6 2,140 10 6 Kaitaia Drainage District—Maintenance costs on completed works (in suspense) .. .. 4,068 18 2 Waihi Drainage District— Maintenance costs on completed works (in suspense) .. .. .. .. 2,373 0 I Balance carried forward on general revenue— Central subdivision .. .. .. 1,070 3 7 Cash in Public Account .. .. .. 8,672 7 8 £665.403 7 4 £665,403 7 4 J. B. Thompson, Under-Secretary for Lands. J. H. O'Donnell, Controller of Accounts. I hereby certify that the Statement of Receipts and Payments and Balance-sheet have been duly examined and compared with the relative books and documents submitted for audit, and correctly state the position as disclosed thereby.—G. F. C. Campbell, Controller and Auditor-General.

Approximate Cost of Paper.—Preparation, not given; printing (700 copies, including graphs, illustrations, and maps), £85.

By Authority : W. A. G. Skinner, Government Printer, Wellington.-—1929.

Price 2s. 6d.]

C.—4.

No. 14 Bucyrus opening out Upper End of G-H Diversion. Nos. 1 and 2 Rockbars in background.

No. 14 Bucyrus excavating No. 1 Rock-bar, equipped with 50 ft. Jib and 1 c.y. Drag-line Bucket.

No. 14 Bucyrus excavating No. 1 Rock-bar.

C.—4.

Drag-line Bucket in Rock, No. 1 Bar.

No. 1 Rock-bar after Drilling and Blasting.

River after opening-out of Upper End of G-H Cut and removal of No. 1 Rock-bar.

a—4.

No. 14 Bucyrus 1 c.y. Steam-shovel excavating G-H Diversion.

No. 6 Diversion and Settlers' Access Bridge, with No. 13 Bucyrus Drag-line on Bank (110 ft. top width).

No. 26 American Steel Dipper Dredge (1½ c.y.) near 0 m. 48 ch. on Mangahahuru Stream Diversion.

C.—4.

Rock-drilling on No. 2 Bar, Wairua River.

No. 3 Priestman Grab Dredge on River Improvement near Lewis Bridge.

Upper End of No. 6 Diversion of Wairua River, and Settlers' Access Bridge, 120 ft. long.

C.— i

PLAN OF KAITAIA DRAINAGE DIST.

_0-4^

PLAN OF HIKURANGI DRAINAGE DIST.

C.-4.

PLAN OF Waihi Drainage Dist.

This report text was automatically generated and may include errors. View the full page to see report in its original form.
Permanent link to this item

https://paperspast.natlib.govt.nz/parliamentary/AJHR1929-I.2.2.2.6

Bibliographic details

DEPARTMENT OF LANDS AND SURVEY. SWAMP DRAINAGE. REPORT FOR THE YEAR ENDED 31st MARCH, 1929, TOGETHER WITH STATEMENT OF ACCOUNTS., Appendix to the Journals of the House of Representatives, 1929 Session I, C-04

Word Count
6,629

DEPARTMENT OF LANDS AND SURVEY. SWAMP DRAINAGE. REPORT FOR THE YEAR ENDED 31st MARCH, 1929, TOGETHER WITH STATEMENT OF ACCOUNTS. Appendix to the Journals of the House of Representatives, 1929 Session I, C-04

DEPARTMENT OF LANDS AND SURVEY. SWAMP DRAINAGE. REPORT FOR THE YEAR ENDED 31st MARCH, 1929, TOGETHER WITH STATEMENT OF ACCOUNTS. Appendix to the Journals of the House of Representatives, 1929 Session I, C-04

Log in or create a Papers Past website account

Use your Papers Past website account to correct newspaper text.

By creating and using this account you agree to our terms of use.

Log in with RealMe®

If you’ve used a RealMe login somewhere else, you can use it here too. If you don’t already have a username and password, just click Log in and you can choose to create one.


Log in again to continue your work

Your session has expired.

Log in again with RealMe®


Alert