Railway Construction.
COST OF LINES UNDER WAY. WELLINGTON, Feb. 1. A statement showing the position of all the railways at present under construction in the Dominion was presented to the House of Representatives today by the Minister of Public Works (the Hon. J. G. Coates). The details given in the statement were as follows: Section Expended Required to Complete.
Kaihu-Dennellys 154,580 16,000 N. Auckd-Ngapuhi 207,568 430,000 N. Auckd-Kiropuni 37,822 350,000 Huarau-Portland 708,091 300,000 Waipu 17,573 134,000 Huntlv-Piikcmiro 139,735 49,000 Wailii-Tauranga 126,704 550,000 Mount Tancatua 733,600 400,000 Napier-Tutira ... 153,133 186,300 Tutira-Wairoa ... — 1,087,000 Wairoa-Frasertown — 68,200 Frasertown-Waikura — 1,025,000 Waikura-Gisborne 253,724 144,600 Waikokopu branoli 118,000 230,000 Okabukura-Matierc 311,000 77,000 Matiere-Tahora — 94,000 Kohuratahi-Tahora 232,000 17,000 Opunako 110,615 330,000 Glenbcipo-Inangabua 33,914 1,320,000 Otira-Bealey ... 1,038,000 518,000 Wharanui-Parnassus _ 2,000,000 Point ElizabethKuniinga 33,758 14,000 Lawrence-lloxboroagb 22,839 327,161 Tuatapere-Orawia 22.800 64,000 Totals ... 4,619,515 11,177,261
Permanent link to this item
Hononga pūmau ki tēnei tūemi
https://paperspast.natlib.govt.nz/newspapers/HOG19220204.2.29
Bibliographic details
Ngā taipitopito pukapuka
Hokitika Guardian, 4 February 1922, Page 3
Word count
Tapeke kupu
134Railway Construction. Hokitika Guardian, 4 February 1922, Page 3
Using this item
Te whakamahi i tēnei tūemi
The Greymouth Evening Star Co Ltd is the copyright owner for the Hokitika Guardian. You can reproduce in-copyright material from this newspaper for non-commercial use under a Creative Commons Attribution-NonCommercial-ShareAlike 4.0 International licence (CC BY-NC-SA 4.0). This newspaper is not available for commercial use without the consent of the Greymouth Evening Star Co Ltd. For advice on reproduction of out-of-copyright material from this newspaper, please refer to the Copyright guide.