Delay not due to repairer
• Regarding the Meyer Bridge at Orautoha: What a cheek to say that Winston Oliver "decided to delay the
work". This was said by roads manager Gerrard Eckard at the Waimarino Community Board meeting. If Mr Eckard had checked he would have found that the Meyer Bridge was already in the process of being repaired. Also, why didn't he ring Winston to make sure all the required materials were on hand for the repair job? As it was the promised wire that was necessary to put through the side boards and onto the bridge dropers didn' t arri ve so Winston used his own wire. The nails that were sent with the timber were too small and again Winston provided longer nails to ensure that the timber was properly secured. I could say more and increase the size of the Bulletin. Mr Eckard. olease eet vour facts rieht.
Heather
Oliver
Permanent link to this item
Hononga pūmau ki tēnei tūemi
https://paperspast.natlib.govt.nz/newspapers/RUBUL19961119.2.18.2
Bibliographic details
Ngā taipitopito pukapuka
Ruapehu Bulletin, Volume 14, Issue 663, 19 November 1996, Page 4
Word count
Tapeke kupu
154Delay not due to repairer Ruapehu Bulletin, Volume 14, Issue 663, 19 November 1996, Page 4
Using this item
Te whakamahi i tēnei tūemi
Ruapehu Media Ltd is the copyright owner for the Ruapehu Bulletin. You can reproduce in-copyright material from this newspaper for non-commercial use under a Creative Commons Attribution-NonCommercial-ShareAlike 4.0 International licence (CC BY-NC-SA 4.0). This newspaper is not available for commercial use without the consent of Ruapehu Media Ltd. For advice on reproduction of out-of-copyright material from this newspaper, please refer to the Copyright guide.