THE HIKUTAIA ROAD.
DELAY IN WORK QUESTIONED; ANOTHER PROMISED START. At Thursday’s meeting of the Ohinemuri County .Council Cr. Robin-, son asked why .work on the Rotokohu rotyl was being gone on with in preference to the Hikutaia road. He understood that Die engineer had been instructed to commence; work on the latter road.
At the request of. the chairman Mr Shaw, t'he acting-engineer, explained that he ha,d continued working on the Rotokohu road, because he wanted to finish with the; use of the crusher there. The crusher at present was fitted with a large jaw suitable for metal on that road, whereas for the Hikutaia road a smaller jaw would have te. be fitted. The Hikutaia road would be put in hand on Monday thq •Ith Inst.
Permanent link to this item
Hononga pūmau ki tēnei tūemi
https://paperspast.natlib.govt.nz/newspapers/HPGAZ19290304.2.8
Bibliographic details
Ngā taipitopito pukapuka
Hauraki Plains Gazette, Volume XXXX, Issue 5395, 4 March 1929, Page 2
Word count
Tapeke kupu
128THE HIKUTAIA ROAD. Hauraki Plains Gazette, Volume XXXX, Issue 5395, 4 March 1929, Page 2
Using this item
Te whakamahi i tēnei tūemi
Stuff Ltd is the copyright owner for the Hauraki Plains Gazette. You can reproduce in-copyright material from this newspaper for non-commercial use under a Creative Commons Attribution-NonCommercial-ShareAlike 4.0 International licence (CC BY-NC-SA 4.0). This newspaper is not available for commercial use without the consent of Stuff Ltd. For advice on reproduction of out-of-copyright material from this newspaper, please refer to the Copyright guide.